| Fecha | Actividad / Material | Fase | Detalle | $ |
|---|---|---|---|---|
| 30/08/2025 | Compras base (cemento, arena, grava, acero, tabique) | G1+G2 | 6 cem, 16 arena, 21 grava, 8 var 3/8, anillos, 1 millar tabique | $9,525.00 |
| 30/08/2025 | Descarga de material (2 ayudantes) | Logística | Bajada a domicilio | $1,000.00 |
| 30/08/2025 | Costales para acopio/mezcla | G1+G2 | Lote | $200.00 |
| 30/08/2025 | Trabajo familiar (no costo) — Descarga 1 | Logística | Papá + Hermano + Tú (valor simbólico $1,500) | — |
| 31/08/2025 | MO — Ayudante (día) | G1 | Armado 4 m de dala | $550.00 |
| 31/08/2025 | Pago MO — Ayudante | G1 | Liquidación día 31/08 | $550.00 |
| 06/09/2025 | Madera/clavos + IVA (entablado) | G1 | 8 tablas, 4 barrotes, clavos 3"/4" | $1,892.01 |
| 06/09/2025 | Anillos 10×25 + Alambre | G3–G4 / Stock | 4.8 kg anillos; 10 kg alambre | $370.00 |
| 06/09/2025 | Polyflex + Mortero 25 kg (6 pzas) | G1 / G2 | Protección + junteo | $1,139.00 |
| 06/09/2025 | Herramienta — Diablito | Logística | Carretilla de mano | $389.00 |
| 06/09/2025 | MO: Maestro (día) + Ayudante (½ día) | G1 | Entablado y colado ~8 m de dala | $825.00 |
| 07/09/2025 | MO: Maestro + Ayudante (día) | G1 | Colado final (total 12 m) | $1,100.00 |
| 07/09/2025 | Pagos MO (informativo) | G1 | Maestro $825 · Ayudante $550 | $1,375.00 |
| 09/09/2025 | Madera mínima: 4 polines + 4 tarimas | G2+G3 | Acceso/altura para muros | $808.00 |
| 11/09/2025 | Compra etapa (cemento/arena/grava/acero/estribos) | G2+G3 | 6 cem, 15 arena, 19 grava, 7 var 1/2, 4 var 3/8, 7 kg 10×15, 30 kg 10×25 | $7,173.00 |
| 13/09/2025 | Entrega recibida — materiales 11/09 | G2+G3 | Hito logístico (sin costo) | — |
| 13/09/2025 | Trabajo familiar (no costo) — Descarga 2 | Logística | Papá + Hermano + Tú (valor simbólico $1,500) | — |
| 13/09/2025 | MO devengada — Maestro + Ayudante (día) | G2 | Terminado muro A CG + muro CP contiguo | $1,100.00 |
| 13/09/2025 | Pagos MO (informativo) | G1+G2 | Liq. pendientes $550 + día $1,100 | $1,650.00 |
| Acumulado de costo (sin duplicar pagos MO) | $26,071.01 | |||
| Categoría | Monto |
|---|---|
| Materiales | $21,107.01 |
| Herramientas | $389.00 |
| MO devengada | $3,575.00 |
| MO eventual (descargas) | $1,000.00 |
| Pagos MO (informativo) | $3,575.00 |
| Total (costo) | $26,071.01 |
| Fase | Material | MO | Tiempo |
|---|---|---|---|
| G1 · Dala intermedia conjunta (12 m) | $2,221.19 | $1,350 | ~1.5 d |
| G2 · Muros + castillos (Grande + Pequeño) | $5,130.45 | $3,150 | ~3.5 d |
| G3 · Trabes/cadenas (G: 4 m + 5+5+4 m · P: 8 m 15×20) | $8,345.20 | $4,050 | ~4.5 d |
| G4 · Losa Panel W (Cuarto Grande 16 m², 8 cm + aplanado) | $16,079.19 | $1,980 | ~2–3 d |
| Total G | $31,776.03 | $10,530 | ~11.5–12.5 d |
| Fase | Material | MO | Tiempo |
|---|---|---|---|
| T1 · Muros + 4 mochetas | $2,116.30 | $900 | ~1 d |
| T2 · 4 castillos 15×20 | $2,169.25 | $1,350 | ~1.5 d |
| T3 · Losa 3×2.5 m (10 cm) + simbra | $4,720.50 | $1,350 | ~1.5 d |
| T4 · Pretil 3.0×0.90 | $808.15 | $450 | ~0.5 d |
| Total T | $9,814.20 | $4,050 | ~4.5 d |
| Concepto | Cant. | Unidad | P.U. | Importe |
|---|---|---|---|---|
| Cemento 50 kg | 6 | pza | $275.00 | $1,650.00 |
| Arena 40 kg | 15 | costal | $75.00 | $1,125.00 |
| Grava 40 kg | 19 | costal | $47.38 | $900.22 |
| Varilla 1/2" (12 m) | 7 | pza | $230.00 | $1,610.00 |
| Varilla 3/8" (12 m) | 4 | pza | $135.00 | $540.00 |
| Estribo 10×15 | 7 | kg | $25.00 | $175.00 |
| Estribo 10×25 | 35 | kg | $25.00 | $875.00 |
| Polín 2.40 m | 4 | pza | $102.00 | $408.00 |
| Tarima | 4 | pza | $100.00 | $400.00 |
| Total materiales (etapa actual) | $7,683.22 | |||
| Frente | Días | Cuadrilla | Importe |
|---|---|---|---|
| G2 — Muros (CG + escalera CP) | 1 | Maestro + Ayudante | $1,100.00 |
| G2 — Castillos (3 pzas 15×20) | 1 | Maestro + Ayudante | $1,100.00 |
| G3 — Armado + Cimbra (parte 1) | 1 | Maestro + Ayudante | $1,100.00 |
| G3 — Armado + Cimbra (parte 2) | 1 | Maestro + Ayudante | $1,100.00 |
| G3 — Colado de trabes | 1 | Maestro + Ayudante | $1,100.00 |
| Total MO estimada etapa | $5,500.00 | ||